Federal court strikes down order keeping Michigan coal plant open
The ruling challenges the use of emergency powers to prevent Campbell’s closure. The legal question remains separate from the plant’s physical shutdown.
Story from September 11, retained after verification for the September 12 morning selection.
The U.S. government cannot invoke an emergency without establishing the conditions required by law. That is the significance of its September 11 setback before the U.S. Court of Appeals for the District of Columbia Circuit, which struck down the order preventing the planned closure of Michigan’s J. H. Campbell coal-fired power plant. [1]
The scope of emergency powers
According to Associated Press, the three judges unanimously concluded that the Department of Energy had exceeded its authority. Michigan, Illinois, Minnesota and environmental organizations had challenged the intervention. The court describes emergency powers as a limited mechanism to be used as a last resort. [1]
The department takes a different view of the grid’s needs. In its justification published on August 14, it presents Campbell as a resource needed during periods of high demand. It cites the risk of insufficient generation in the region served by MISO and the need to keep capacity available. [2]
A plant still operating
The extension order published in August directed MISO and Consumers Energy to preserve the site’s availability from August 17 to November 14. It provided for operation that would take costs into account. This succession of administrative decisions explains why a ruling on the challenged order should not automatically be treated as an immediate shutdown of the facilities. [3]
Consumers Energy said it was continuing operations while analysing the ruling, Associated Press reports. At the time of the report, the plant had therefore not been announced as closed. The operational and legal consequences of the decision for subsequent administrative measures remain to be determined. [1]
Grid reliability and the legal framework
The case raises two related but distinct questions: how to ensure electricity supply, and under what conditions Washington can require a power plant to remain open. The government addresses the first by invoking grid reliability; the ruling emphasizes that this objective must be pursued within the authority granted by law. [2]
Perspectives compared
The court finds that the Department of Energy exceeded its authority and failed to establish the required emergency. [1]
The government argues that the plant should remain available to meet peak demand and prevent outages. [2]
Consumers Energy says it is continuing operations while reviewing the ruling. [1]
Sources and documents
- [1] Associated Press / Local 10 ↗September 11, 2026
- [2] U.S. Department of Energy ↗August 14, 2026 · government position
- [3] Department of Energy · order 202-26-39 ↗August 14, 2026 · extension order